flintgreasewood

Members
  • Content count

    141
  • Joined

  • Last visited

  • Days Won

    16

Everything posted by flintgreasewood

  1. A series of mud slides seems plausible. That would allow for some settling and deposition of silt/muck layers between events.
  2. Late December last year I began digging a 6' x 6' prospect shaft about 100' downstream from the original Cobb prospect shaft. Armed with a 30 lb electric jack hammer, a couple of shovels and my nifty 1/2 size home made "Fairbanks self dumping bucket" system I worked my way down through frozen muck and eventually a 10' gravel layer to bed rock at 62'. On my way down I encountered layers of tangled branches and trees up to 6" in diameter. After 40+ feet I hit fine sand and scattered patches of gravel, fossil bone fragments, then complete bones. I was anticipating these finds but the excitement of actually finding them was intense. The first chunk of mammoth tusk nearly put me over the top. Progressing downward, the bones became less frequent and the pay gravel more dense. I had been told that a jack hammer would be ineffective in frozen gravel. Good I don't listen to everything I hear; it busted up almost as easy as the muck. The gravel graded into fractured and decomposed bed rock and I knew I had finally reached my goal...10 months after starting the project. Before freeze up I was able to wash 5 yards of pay and the result was encouraging. I'll have to wait till late spring to resume processing what I brought up before and what I can hoist this winter. Now it's late November and all is solidly frozen above as well as below ground. Since bottoming out in the shaft I've been devoting most of my time to upgrades above the shaft in preparation for winter work. Also I had to take a part time job in town to help pay for the added expense of moving to a small cabin also in Fairbanks. What little time I've been able to devote to underground efforts have been to expand my working space. On the way down I managed to increase the dimensions of the shaft from 6' x 6' to over 7' square. The plan is to continue out to 10' square before I begin pushing the drifts across the valley. Jack hammering straight down is relatively easy compared to working horizontally and even vertically. Sufficient pressure is difficult to exert out of position so I began working on ideas to free the gravel other than by the traditional steaming or blasting to reduce the great amount of physical labor involved with jack hammering. Suffice it to say, I'm making good progress in those efforts. I'll report on this process in months to come.
  3. Chris, no glaciers in this area. Also if it had been a glacier all the bones I'm finding mixed in the gravel would be well ground up
  4. I worked for an operation that used a very large rubber lined pump to suck the gravel coming off a 250 yd per hour trommel The 1/2"- slurry was pushed about 75' through an 8" pipe then up 10' on to a monster jig. It took a 100hp motor to run the pump but it sure did the job. I'm sure you could go smaller but you're still going to have to have some pretty heavy horse power.
  5. Not an awful lot to report. I'm about 9' in my drift which is about 5' wide and 5' 6" high at the top of an arch. My gravel is very atypical with large lenses of pure muck in between a jumble of chunky, fine and ground up shist bedrock, large cobbles, angular and rounded quartz and a smattering of intrusives. There's no bedding or layering except for the muck and I even have bones almost to bed rock, one of those being a young mammoth jaw complete with two teeth found 2' off bed rock. It's quite a conundrum. And the gold is not primarily just off bed rock but spotty and scattered throughout the entire column. Got any ideas? Heavy flood event?? I'm also continually making changes to my heat rods for the gravel thawing. My latest iteration should be ready to test out in about 2 weeks. From calculations and prior experience I'm expecting some really effective thawing. I'm also improving my drilling system making it faster and less labor intensive. My bucket hoist has been working nearly flawlessly. I'm ready for the cold to leave though I'm not looking forward to fighting with runoff again this year. Got some ideas how to mitigate it. More soon. Thannks all for your continued interest.
  6. Doug. That sounds like a plan. How far out are your claims? How long have you had them?
  7. Hey guys, sorry for taking so long to respond. I'm back down in the hole where it's much warmer than top side. Finally got all systems working well enough to initiate another round of drilling and thawing in my main drift. Unfortunately, my heat rods weren't working like I had hoped they would and produced an uneven thaw. Consequently I had a fairly thick wall of frozen gravel on the face and well thawed gravel behind which necessitated a good bit of jack hammering to clean it all out. So I brought all the rods home and reworked them so they'll heat more evenly and also run a good bit hotter. I'll be testing them over the next two days. My young help disappeared when the snow and cold hit and put an end to above ground work. I may get them back soon. The began putting down a new shaft about 150' from my shaft which I'll eventually connect to via my drift. We're thinking the main pay streak is much closer to being below the new shaft. I'm developing a system for operating my hammer drill that allows me to simply set up the various support members, position the drill and then just turn a crank handle to either pull the drill bit into the wall or retract it. I've already drilled about 20 holes using the system and now I'm just simplifying it. Hopefully soon I can include some videos and photos of the operation. Well, that's about it for now. Stay tuned.
  8. JR Thanks for your continued interest. I'm back in town for the fall and winter[back on line] so I can update easier. It was a slow season for pushing the drifts in my shaft. I spent much of the summer upgrading infrastructure, as it were...new gin pole, new shaft deck, new dead man, etc. Also had water issues that have been so aggravating I just didn't want to be down in all the wet. I did get some thawing done and am very pleased with the performance of my home made thawing rods. I'll start back in the drift as soon as things freeze up good. We're also prospecting an old mine's dump piles [not tailings] and will try to keep that going even after freeze up. Got a couple of young guys helping me out now. Sure nice to have the extra muscle, enthusiasm and company.
  9. I'm looking for someone to mine roughly 2 miles of virgin permafrost placer stream valley close in to Fairbanks. The overburden ranges from about 45' to 80' so it would require an operation not afraid of going deep. Pay gravels are 8' to 10' and contain gold for nearly the entire horizon. Though the ground has not been drilled, there are several prospect shafts that indicate values of a minimum of 1 oz per 30 yds.. The history of the creek below my claims is rich and much research has been done re. geology and production. Ground is a mile from major highway and town is less than 1/2 hour distant. A prospective operation will need to drill the ground and have large dozers w/rippers, rock trucks or dragline and excavators. There is a large spring that can supply sufficient water for processing. If interested contact Kurt
  10. Hey, Leonard...good to hear from you again. Been past that mill many times on my mountain bike. Just love James Canyon and all the mining in that area. It would be great to see renewed activity up there again, but bucking the greens of Boulder County is pretty daunting. Come on back up here to Fairbanks and see my operation this summer.
  11. Steve, Your interest seems strong enough that we should carry on further discussion via e-mail. Mine is flintgd@aol.com. Talk soon.
  12. Hi, Steve, Harry, Chris and other interested miners, My first reaction in response to Steve's last post is: where does the money come from to drill, rip with a dozer, excavate, haul material, build access road, site grade, etc? It's going to take someone or some operation that has a very good knowledge of the immediate area and its potential and, therefore, is willing to take the risk to get some firm numbers. Next, frozen muck drills fast, but 80' holes are still not cheap. I'll try to get some costs. Working with a dragline is probably the most cost effective way to remove overburden and currently there is a good possibility of a 2 1/2 yarder available. If operations were to begin at the furthest downstream point that would be just past where the two feeder creeks joined, thereby combining two pay steaks. That would surely be the richest ground. Drilling might best begin at the division of the creeks. I'd like to think that by summer's end I'll have good knowledge of the pay on the upper end of Vault [more than 1/2 mile above the junction] from drifting out of the shaft I've put down. So, how serious are you about my ground, Steve? What could you bring to a venture? How similar is a "syndicate" to a partnership?
  13. You are right, Chris, about the thawing muck. It certainly presents problems but there are mining operations in the Fairbanks area that routinely tackle frozen overburden as deep or deeper than my ground. Frozen muck rips easily, so you do all your overburden removal beginning in the fall after freeze up. Take a break in December and January and get back with it till June when it really warms up. There's plenty of room in the valley to stack overburden. So by June you have a patch of pay gravel 150 to 200' wide by, say 200 feet deep by 10' thick, That's about 15,000 cu yds. Based on historical reports of gold produced downstream on Vault Creek I'm convinced the pay could easily run over $100. per yd. That would come out to around , $1,500,000. Of course drilling first is essential, and what I find in my drift tunneling will enable us to put some numbers where up to now there is only speculation.
  14. That's exciting. I'll be watching your progress too.
  15. Hey guys I have approximately 10 feet of gravel on top of bed rock. I'm only beginning to run my drifts across valley so I'm not able to say what the angle of bed rock is yet. Now I'm recovering from back surgery [relatively minor] but it's going to keep me from any vigorous mine work for several weeks. Ahhh, patience!
  16. Hi Chris It's almost February and I'll soon be starting my cross valley drifts. In anticipation of increased material removal I am beefing up and enlarging my hoisting system. Should be an exciting season. Good luck to you
  17. Welcome to the Forum. That's a pretty slick looking piece of equipment and well made too. Aluminum? Where are you located?
  18. JR, Good to hear back from you. The seepage into the shaft ended shortly after freeze up. All is nice and dry down below. I'll be digging a substantial trench up stream this spring to hopefully divert any flow into the shaft next summer. Let's hope it works.
  19. Thanks, Doug I hope my efforts serve as an encouragement to other current and future drift miners. I'm hoping to develop simple systems that can be utilized by even just one person to successfully mine underground.
  20. A few months ago I was frustrated with my inability to get anywhere with the old Cobb prospect shaft. Between then and the end of 2015 I fiddle farted around with reconfiguring my steam system and making my work shacks semi habitable in the extreme cold that was to come. When the temperatures here in the interior of Alaska insisted on staying well above 0 it came into my head to put down a new shaft. Earlier in the year I had carefully walked the area directly downstream from the old shaft looking for possible sites. Though the ground was now covered with 2 feet of snow I easily relocated the chosen spot. With my trusty aluminum scoop shovel I removed the snow from a large area and went at the frozen moss and brush with a pick adz. Darkness crept in slowly even though it was only 4:30 so I ran a 100' extension cord from the camp, set up my flood lights and worked on into the night. Integral to a new shaft would be a new gin pole and I figured I'd have to cut down a large spruce, drag it a couple hundred yards, jackhammer out a pit in the frozen ground and rig up a hoisting system to raise it up in place. The prospect of all that work caused me to rethink the positioning of the gin pole and it hit me that I merely needed to run my highline to the tallest, sturdiest spruce 90 degrees from where I had originally thought to place it. I wouldn't need a pole that would have to be in service for many years...just a year or two. And if I needed something more substantial later on I could take care of that in the spring. I found the right tree, brought in my 18' ladder and proceeded to position eye bolts and guy wires for support.The high line would need to be anchored behind the shaft and to do that I had to dig a pit in which to set a "dead man". However. the angle of the high line over the shaft area would be too low to allow a bucket to exit and clear the shaft wall. I had to rig an elevated support, a "quad pod" of spruce poles between the anchor point and the shaft that effectively raised the high line 5' above the shaft. I'll have to hang the bucket to determine if the high line is elevated enough. Once I had the high line in place I could begin filling the dead man pit, but with what? I didn't want to use frozen muck with its high water content. I opted for gravel and the best and closest source for that was the pit we've been slowly excavating for our outhouse. Of course that gravel would be frozen so I loaded up the generator, jack hammer, shovels and weed burner in the sled and zipped on up to the cabin. The jack hammer doesn't work properly when it's cold and that's where the weed burner comes in. I spend a few minutes warming up the jackhammer and my gloves and everything works much nicer. I underestimated the amount of gravel I needed to fill the dead man pit and had to return for another load. To insure a strong dead man I dumped in 10 gallons of water to freeze it into one solid block. Now I'm working on an electric hoist and as soon as I can get it operational I'll be able to begin actually digging out the shaft.
  21. For those who have been following my odyssey some real progress has been made on my new shaft in the past two months. It's been one hard slog to jack hammer my way down to 55' but persistence is paying off. I'm now in mixed gravel and muck and will be into some gold in a few more feet. The gravel is proving to be more difficult to jack hammer than I had hoped though it varies around the shaft. Some will be almost dry and breaks up easily and other places it will be as hard as concrete. What keeps things interesting though is the fossil remains I'm uncovering. Just today I pulled out a mammoth metatarsal [toe bone]. Last week I chipped out a 5 lb. chunk of mammoth tusk. It's likely I'll be finding full tusks as I drive the drifts. Hoisting is going quite well though I have to watch the weight in the bucket as the gravel is substantially more heavy than the muck and my motor overheats if I overload or send up a bucket without letting the motor cool down a bit. I'm getting ready to run some heavier electrical wire so that should help with voltage drop. We'll be building a new boiler house shortly and setting up the steam system though we may be experimenting with some different methods of thawing. More to come soon.
  22. Here's a brief update on my work at Cobb prospect this season. I'm now down to the 40' level in my 6x6 shaft. It hasn't been easy with problems of spring snow melt, a snapped gin pole, endless modifications of the hoisting system. trails turning to mud bogs. dying jack hammers and just plain gettin' older and tireder. The gin pole situation was nearly fatal as it allowed the full bucket to be free to return to the shaft and fall 25' to land right at my feet...a real heart stopper. God is good and saved me from harm. I now have a full size 2" x 10" x 10' plank that I used as a shield every time I hoist or lower a bucket. Don't wish to put God to the test again so soon. Then I had to cut and drag into position a new and larger pole to replace the broken one. Raising the 34' spruce with tripods, come along, a small electric winch and lots of guy wires was no easy trick, but I managed. The trail turned bog forced me to find a new high and dry route to the prospect but that entailed crossing Vault Creek and two little pups. To do that I had to build three bridges, two of them 30' long and one 10'. That's a lot of 4" x 4' poles. While pitching some of those poles I threw out my back and an MRI determined I ruptured a disc in my lower back. So I've been limping around for 6 weeks with a numb foot [pinched nerve] and am awaiting laser surgery in late Aug. Fortunately, I am not in pain and can still work in the shaft as normal. I now have all systems working to near perfection with a new jack hammer and even a small hoist dedicated to hauling me up and down the shaft instead of having to use the ladder...a real energy saver. Just the other day I noticed my bucket refused to lower into the shaft. I determined the dead man that was anchoring the main high line was giving way so that the line was too slack. Fortunately, I had several 3 1/2 foot lengths of 1" rebar that I had ground points on. I drove three of them in line 3' apart and connected them base[ permafrost frozen just below the moss] to top and attached the high line to the first one. It has so far proven to be a fine dead man setup. I made sure the posts are well insulated and protected from possible rain. It's been a lot of hard work and sometimes discouraging with the slow pace I am going but I'm learning patience. I have only 16 to 18 feet to go to hit gravel and then things really get exciting. I'll let you all know when I get there. Till then, have a great rest of the summer mining season.
  23. Thanks, JR I'm confident it's going to be a very exciting year
  24. sorry about all the repeat entries. not sure how that happened. three photos also not included. i'll try soon to get them up.
  25. As Jack Nicholson declared in "The Shining"..."I'm back!!" Finally I have some real progress to report on. It was early January when I began my new shaft at Cobb Prospect. Most of my efforts then were done in darkness and below 0 temps but the excitement of a fresh start kept me on task. Now it's nearly spring with lots of light and often above freezing days. Actually, nearly the entire winter offered more than bearable and often downright pleasurable working conditions. Setting up my electric hoist was not a simple matter; should I have expected different? The hoist came with a 3/4hp DC motor and controller. The motor was good but the controller wasn't, so I gave up and switched to a 1hp AC motor I found on Anchorage Craigslist. It fit the speed reducer fine and it looked like I was in business but when I put the juice to it the generator struggled and the motor barely spun. Being somewhat ignorant of many things electrical I succeeded in letting the smoke out of the motor. And as everyone knows, motors are run by pre installed smoke at the factory. When that smoke gets out the motor quits working. Simple! I brought it in to the local motor repair shop and to my relief I had just burned out the capacitor. But I also got the news that my generator was under powered. A friend said he had a 4000watt out at his mine site that I could borrow so we made the 50 mile trip out [ran out of fuel on the way] and the next day I hauled it down to the prospect. I should have paid more attention to the motor technician. A 1 hp motor requires 4400 watts for initial startup. The replacement didn't cut it. I didn't have the funds to plunk down on a new 5500 watt machine even a cheap one from Lowes but I applied for and received one of their cards and was able to get it on credit. The one I picked was marked way down as it had been bought and returned because it was too small. It was also a propane only model but I figured I could get along with that. So I hauled that one down, unpacked it and read the owner's manual. When I saw how much propane it would consume in a 4 hour run time at 50% power I was stunned. I'd have to spend at least twice what I would have to with a gas model. I packed it back up, returned it, picked up a gas model and hauled it down to Cobb. My plan was to control the hoist with a cheap reversing drum switch I had used in the old shaft. The wiring was more complicated with the new motor and it took me hours of analysis to figure out how to set it up. It didn't work, most likely corroded contacts. I was fed up and went searching for an industrial grade switch, found one on an Ohio craigslist and bought it. In the interim I wanted to use the hoist as I was now deep enough in the shaft that it was getting too difficult to pitch the frozen chunks of muck out by shovel. I realized that I could operate the winch by simply making a setup where I would have an on/off switch and two terminals that would allow the swapping of the reversing wires fit with alligator clips. It worked. I wanted to use a standing live spruce for my gin pole and had available but one that was tall enough I soon realized that the angle of the carrier high line was too flat between the head frame and the gin pole. For a temporary solution I erected another gin pole mid point on the line which provided a steeper slope which would allow the bucket to generate enough momentum on it's return to trip the release catch. That didn't help. Next was to increase the hoist speed by doubling the drive gear pitch. The additional speed and reduced trip time was great but still wasn't fast enough for the bucket to release. I noticed that if the bucket dump chain got caught and held the bucket still for even a couple seconds, enough slack in the hoist line was generated so that when the chain was loosed, the bucket ran free with enough speed to release at the trip pin. I rigged up a catch point using a plastic barrel placed under the trip line. That worked...most of the time, but not all the time. Adding more weight to the bucket didn't seem to help. What next to try? I checked the carrier for possible issues and found an obvious problem . A retracting spring was too stiff and held the catch mechanism too firmly in place for the trip pin to move it. Changing the spring helped but still didn't completely solve the issue. I removed the carrier, took it home removed just one side plate so I could manually operate the various parts, something I had never done before. It was easy to see that a bad angle on one of the catch pieces made it very difficult for it's mating part to slide off to allow the bucket to release. Those fixes helped even more but I'm still not quite satisfied; I need the bucket to trip every cycle, not just 90% of the time. Since I was not happy with my gin pole setup, I decided to erect an even taller one next to the original and using that one to hoist the new one in place. Using my chain saw winch I dragged the 28' black spruce down the hill through 2' of snow, reattaching three times to make bends in the route through the standing trees. That was, by far the hardest part of the job. Hoisting the new pole required that I work from a ladder propped against the old one. A number of guy wires connected to spruces with ratchet straps and turnbuckles were already in place including the main carrier line and all had to be loosened, some removed and repositioned and retightened numerous times. In time I was able to separate the two poles held together by straps and cut the old one down, leaving the new, bigger and taller one standing alone. More wire adjustments brought it straight and true. I had managed to dig the shaft down to 8 feet [that's 8'x8'x8'] and it was time to put in the cribbing. During February I began harvesting large black spruce, cutting them into 8' lengths, carrying or dragging them through the deep snow to a sled. I was able to stack 8 or 9 of them to be hauled behind my snow machine down to the shaft site. As I prepared to start setting the logs I could see there was not going to be space enough for the bucket to ride up and down the shaft freely with a cribbed wall. Evidently I would either have to enlarge the shaft on the one side by at least a foot, or move the gin pole. I almost couldn't bear the thought of another gin pole change, but the thought of jack hammering and removing an additional 3+ cubic yards of frozen muck was even more unpalatable. I knew the gin pole was setting not in a deep hole but merely just below the moss on frozen muck. If I cleared out a path through the snow and moss, I could put a comealong on the pole and simply drag it to the new spot 5' away. I just had to keep adjusting tension on all the wires supporting the pole. The entire operation took less than 3 hours and went without a hitch. Amazing! I now had plenty of room for the bucket to operate. Cribbing began with placing two over length base logs in place. To accomplish that I had to jack hammer notches in the walls at the bottom of the shaft. Sounds easy? It took more than half a day to get them set and I was whooped. Successive log courses went in relatively smoothly and I'm now up to just over half way to the surface. At the 4' point I began placing glass wool insulation between the walls and crib logs which are set to make a 6' square shaft. So that's where things stand. Oh, I did receive the new drum switch and found it had a part missing that kept it from reversing. Just yesterday I made that part in the machine shop where I am doing temporary contract welding.